Finance and General Purposes Special Committee Minutes 11 July 2024
Finance and General Purposes Special Committee Minutes 11 July 2024
Corporation and Committee Minutes- Finance and General Purposes Special Committee Minutes 11 July 2024
Minutes of a special meeting of the board of Leicester College corporation: Finance and general purposes committee
Held on 11 July 2024 online via MS
Present: Danielle Gillett (Chair), Chan Kataria, Lesley Giles, Lee Soden, Verity Hancock
In Attendance: Louise Hazel - Director of Governance and Policy, Shabir Ismail - Deputy Principal/CEO, Shaun Curtis - Director of Estates and Campus Services
Declarations of interest
Verity Hancock declared an interest as a member of the Office for Students (OfS) Board.
Apologies for absence
Apologies for absence were received from Robert Radford
Capital projects update - Aeronautical
3.1 The Deputy Principal and Director of Estates and Campus Services presented
an update on the aeronautical project. The following points were highlighted.
3.1.1 The budget remaining for the project, funded by the OfS, was £4.34m
after other projects had been completed. Tenders had been invited from
six potential contractors, two of which had withdrawn. The four remaining
tenders had come in at between £4.38m and £5.02m net.
3.1.2 Value engineering had brought prices down with GF Tomlinson’s tender
at £4.124m and it was proposed to proceed with GF Tomlinson as the
best priced tender. The company had recently completed a £15m
aeronautical and space institute for Lincoln College.
3.1.3 Taking into account gross costs and a contingency of £125k, the total
cost of the project would be £5.074m. A further £125k of furnishings
fittings and equipment could be saved leaving a shortfall of £859k.
3.1.4 It was proposed to vire £374k from the capital budget set aside for
roofing works to this project; the roofing works could be deferred. This
meant an additional £475k was needed from reserves to cover the
shortfall and enable the project to proceed. The Committee was asked to
agree the additional capital expenditure.
3.1.5 The College would now be contributing 20% of the project cost with the
remaining 80% from the OfS.
3.2 Governors asked a number of questions including:
3.2.1 What the original planned College contribution was. It had been
10%.
3.2.2 What would happen if the additional capital expenditure was not
agreed? The Committee could choose not to agree it but this would
restrict growth and the ability to enter an area of delivery which was
lucrative and would be a genuine USP for the College. There was no
Level 4/technical pathway for space. It was frustrating that the LLEP
and other local bodies had not seen the benefits and supported the
plans with funding.
3.2.3 The College should push for more funding from the OfS. It would
continue to do so although the OfS had indicated that no additional
funding was available.
3.2.4 The cost increases were always going to be likely given the current
market but the project should go ahead. Noted. It was possible that
more funding might become available.
3.2.5 The new government’s approach looked promising with the
potential for an industrial strategy, priority sectors including high
level engineering, strengthened devolution and local investment, all
of which might unlock opportunities for further funding.
3.2.6 The College should make it known to anyone who might be able to
provide funding that additional funding was needed so that should
funding become available the project was an obvious choice. There
was nothing to lose in doing so. The College was working with the
University of Leicester. It would also make clear to the OfS that not
getting additional funding might mean the project needed to be scaled
down. The Vice Principal would be meeting with Phoebe Dawson
(Leicester and Leicestershire Business and Skills Partnership) soon and
would raise it with her.
3.2.7 Was there any scope for working with Leicester University to
identify a named sponsor? This could be explored.
3.2.8 The short term versus the long term needed to be considered.
There was a good case that this was integral to growth although
there were no guarantees. What would the impact be on the bottom
line, the EBITDA and the financial rating? This was capital
expenditure so there would only be a small hit on the bottom line in
terms of depreciation. The EBITDA would be slightly weakened but not
to any significant extent and the financial health would still be good.
3.2.9 Previously the College had been bold and taken decisions to invest
out of a position; this was a similar situation and there was the
potential for access to funding which might not be available again.
Agreed.
3.2.10 Based on previous experience, was there confidence that the
contingency was sufficient? The greatest point of uncertainty was
usually at the tender stage; once the contract was awarded, the
architects who had worked with the College before and knew the market
well would be critical in helping control costs. Having previously built the
motor vehicle block next to site of the new building, there was also
confidence that there were unlikely to be any unknowns in respect of the
land. There were no archaeological issues. Since it was a new building
here would be no need to decant which could add to delays.
3.2.11 Why was a decision needed now? The preferred contractor required a
purchase order to be raised by 12 July in order to commit to the project
and start work. A meeting with the architect would also be taking place
on 12 July. The Committee needed to approve the proposed expenditure
above the previously agreed capital budget.
3.2.12 Had sufficient due diligence been undertaken on the contractor and
did they have the capacity to deliver? There had been some issues
with the company’s delivery of reactive work in other sectors. The
company had two divisions and the building division was considered low
risk. Its recent work at Lincoln College on a similar project provided
some reassurance of its capacity to deliver.
3.3 The committee:
3.3.1 Noted the tender prices received for the aeronautical project.
3.3.2 Approved the additional spend of £859k on the project through
cash reserves, £384k of which would be vired from another project.
3.3.3 Requested a report back at the next meeting.
Date of next meetings
3 October 2024